The four BOT-based garbage incineration power generation projects invested and built by ENFI are located in Wuxi, Xiangyang, Harbin and Ganzhou respectively with cumulative daily waste disposal capacity of 5,600 tons. Furthermore, ENFI has completed the engineering design for over 30 garbage incineration power generation projects. Among them, 20 projects have a production capacity exceeding 1,000 tons. These projects are distributed in more than 20 cities in China, and their total daily waste disposal capacity exceeds 30,000 tons which accounts for 20% of the total garbage treatment capacity of constructed garbage treatment projects in China.

Rich engineering experience

BOT Projects

No.

Location of construction site

Name of project

Capacity

Mode

Remarks

1

Guangdong

Shenzhen Bao’an Laohukeng Domestic Garbage Incineration Power Plant (phase II)

3000t/d,4×750t/d, 2×30MW generator units

Consultation

Put into production in 2012

Shenzhen Baigehu Domestic Garbage Incineration Power Plant

1200t/d,3×400t/d, 2×15MW generator units

Consultation and design

Under construction

2

Hebei

Qinhuangdao Domestic Garbage Incineration Power Plant

1000t/d,2×500t/d, 2×9MW generator units

Consultation and design

Put into production in 2010

3

Hubei

Wuhan Hanyang Guodingshan Domestic Garbage Incineration Power Plant

1500t/d,3×500t/d, 2×20MW generator units

Consultation and design

Put into production in 2013

4

Jiangsu

Yangzhou Domestic Garbage Incineration Power Plant (phase I)

1000t/d,2×500t/d, 2×10MW generator units

Consultation and design

Put into production in 2010

Yangzhou Domestic Garbage Incineration Power Plant (phase II)

1×610t/d, 1×12MW generator units

Under construction

Yixing Domestic Garbage Incineration Power Plant

500t/d, 2×250t/d, 1×9MW generator units

Put into production in 2007

Wuxi Huilian Domestic Garbage Incineration Power Plant

1200t/d,3×400t/d, 2×12MW generator units

Put into production in 2006

Suzhou Domestic Garbage Incineration Power Plant (phase I)

1050t/d,3×350t/d, 2×9MW generator units

Design

Put into production in 2006

Suzhou Domestic Garbage Incineration Power Plant (phase II)

1000t/d,2×500t/d, 1×20MW generator units

Consultation and design

Put into production in 2008

5

Liaoning

Dalian Domestic Garbage Incineration Power Plant

1500t/d,3×500t/d, 2×12MW generator units

Consultation and design

Put into production in 2012

6

Shandong

Jinan Domestic Garbage Incineration Power Plant

2000t/d,4×500t/d, 2×18MW generators

Consultation and design

Put into production in 2011

Linyi Domestic Garbage Incineration Power Plant

800t/d,2×400t/d, 1×25MW generator units

Put into production in 2008

7

Sichuan

Chengdu Xiangfu Domestic Garbage Incineration Power Plant

1800t/d,3×600t/d, 2×18MW generator units

Consultation and design

Put into production in 2012

Chengdu Luodai Urban Domestic Garbage Incineration Power Plant

1200t/d,3×400t/d, 2×12MW generator units

Put into production in 2008

8

Tianjin

Tianjin Guanzhuang Domestic Garbage Incineration Power Plant

1000t/d, 2×500t/d,2×10MW generator units

Consultation and design

Under construction

9

Yunnan

Qujing Domestic Garbage Incineration Power Plant

800t/d, 2×400t/d, 2×12MW generators

Consultation and design

Put into production in 2010

10

Zhejiang

Ningbo Fenglin Domestic Garbage Incineration Power Plant

1050t/d, 3×350t/d, 2×6.8MW generator units

Consultation and design

Put into production in 2001

Wenzhou Yongqiang Domestic Garbage Incineration Power Plant

900t/d, 4×225t/d, 2×7.5MW generator units

Design

Put into production in 2003

11

Hainan

Haikou Domestic Garbage Incineration Power Plant Expansion Project

1200t/d,2×600t/d, 2×12MW generator units

Design

Under construction

12

Shanxi

Shanxi Jincheng Domestic Garbage Incineration Power Plant

500t/d,9MW generator units

Consultation and design

Under construction